Energy Recovery Facility Construction Works for the North: contract awarded

Post-award. Commercial timing: Post-award, stage 6 of 6

The main contract has been awarded. Downstream packages may follow.

Contract value
£1,250,000,000
Signal date
13 Nov 2026
Borough
Tottenham Hale
Client
North London Waste Authority

On record

Published by
Find a Tender
Recorded
13 Nov 2026
View original record(opens in a new tab)

Our reading — automated

What we found

North London Waste Authority has awarded a contract for Energy Recovery Facility Construction Works for the North London Heat & Power Project ("NLHPP") - Agreement dated 24 January 2022 as previously amended by Variation Agreement No. 1 dated 27 June 2023 and Variation Agreement No. 2 dated 26 July 2026. It is proposed to further amend the Contract by way of a draft Settlement and Variation Agreement No. 3 intended to be signed on 14 December 2026 to Acciona Industrial S.A., valued at £1250m.

What it may mean

The main contract has been awarded, making the signal more relevant to downstream subcontractors, suppliers and recruitment businesses than to principal contractors.

Who it suits

Construction recruitment
High

Prospect state

Approach window

Prospect

Acciona Industrial S.A.

Acciona Industrial S.A. has been appointed to deliver the works, giving recruiters an identifiable delivery organisation to monitor for mobilisation and staffing demand; no hiring requirement is stated in the record.

Watch for

Mobilisation and package or subcontractor awards, and approach relevant delivery teams ahead of mobilisation.

Want us to watch it for you? Follow this project and we'll email you when we record the next signal.

Follow project →
Specialist contractors
Relevant

The main award is complete, which is when downstream package opportunities typically form.

Building products
Relevant

Suppliers may still be relevant to package delivery after award.

Also in this journey

  1. 13 Nov 2026Energy Recovery Facility Construction Works for the North: contract awardedThis signalPost-award. Commercial timing: Post-award, stage 6 of 6
  2. 13 Nov 2026Energy Recovery Facility Construction Works for the North: planning conditions submittedEmerging. Commercial timing: Emerging, stage 3 of 6

Still unconfirmed

  • Appointed subcontractors
  • Delivery programme
  • Package procurement
  • Project team

The project

Energy Recovery Facility Construction Works for the North

North London Waste Authority programme covering Energy Recovery Facility Construction Works for the North London Heat & Power Project ("NLHPP") - Agreement dated 24 January 2022 as previously amended by Variation Agreement No. 1 dated 27 June 2023 and Variation Agreement No. 2 dated 26 July 2026. It is proposed to further amend the Contract by way of a draft Settlement and Variation Agreement No. 3 intended to be signed on 14 December 2026.

Type
Infrastructure
Stage
Pre-construction

Follow this project by email

We will send you the next signal we record against it. You confirm by email first, and every update carries a one-click unsubscribe.